HMS Vanguard In CHS
Posted: Fri Jul 08, 2005 1:35 am
In the mod the vanguard has 12 5.25s when in reality it had 16
ORIGINAL: The Dude
In the mod the vanguard has 12 5.25s when in reality it had 16
ORIGINAL: The Dude
In the mod version i was playing the Vanguard had 12- 5.25s, 6on the left 6 on the right in double mounts.
As completed the Vanguard had 16 5.25s in the same configuration as the KGV class.
ORIGINAL: Don Bowen
ORIGINAL: The Dude
In the mod version i was playing the Vanguard had 12- 5.25s, 6on the left 6 on the right in double mounts.
As completed the Vanguard had 16 5.25s in the same configuration as the KGV class.
I can not find any reason that we had three twin mounts per side instead of four and I guess it was an error. A number of people contributed to the specifications, which were difficult to isolate in 1945 for a ship that was not actually completed until 1948.
But it does look like four twins per side is correct and I will add the fix to the change list. If anyone has other data, please let me know.
ORIGINAL: AlaskanWarrior
Actually Don, the Vanguard was commissioned in 9 Aug 1946. Commissioning actually indicates a completed status (now she probably needed worked up, post-commissioning workups, etc. One have to admit that her auto-loading 5.25's probably needed some tweaking, as well as her advanced fire control. However, I have to question the inclusion of this ship in the database and even the inclusion of the Midway Carriers? Even in a extended scenario into 1946 these ships wuold not be able to contibute.
Oscar Parkes, British Battleships 1860 to 1950, pegs it at April 1946. Every source I can find places her in completed and in commission by no later that autumn 1946. Parks also mentions that she was in refit in 1947-1948, which might be when the fancy 6 barrelled 40mm were installed. Parkes lists her originall 40mm as 11 twin mounts.ORIGINAL: Don Bowen
ORIGINAL: AlaskanWarrior
Actually Don, the Vanguard was commissioned in 9 Aug 1946. Commissioning actually indicates a completed status (now she probably needed worked up, post-commissioning workups, etc. One have to admit that her auto-loading 5.25's probably needed some tweaking, as well as her advanced fire control. However, I have to question the inclusion of this ship in the database and even the inclusion of the Midway Carriers? Even in a extended scenario into 1946 these ships wuold not be able to contibute.
Lenton, in British and Dominion Warships of the Second World War, gives a completion date of April 25, 1948. A CHS contributor from England provided the estimates for her armament as of an (originally planned??) early completion. Phil has not been on the forum in a while and I really can not answer too many questions without his help.