Unit Production Times

Post by RyanCrierie »

I'm wondering if there's a way to change them to be more realistic, and to tie it in with a startup script enabling the player to select from pre-war "Cards" to play that change your "future units" that arrive when you start a scenario.

Like for example: "Build more U-Boats than historical, so you have more submarines available in 1939/1940 at the expense of say, armored units, etc"

For example, here's the German order dates for submarines arranged by date and # ordered then.

Image
User avatar
RyanCrierie
Posts: 1327
Joined: Fri Oct 14, 2005 7:15 am
Contact:

RE: Unit Production Times

Post by RyanCrierie »

U-Boat Orders broken down by Type/Class:

Image
User avatar
RyanCrierie
Posts: 1327
Joined: Fri Oct 14, 2005 7:15 am
Contact:

RE: Unit Production Times

Post by RyanCrierie »

NOTE: Add from between 100 to 200 days (depending on time period) for the boat to undergo training and be certified to go on its first war patrol following commissioning.

Type IA: 491 Day Lead From Order to Commissioning
(Only two built; fastest was built in 476 days from order to commissioning)

Type IIA: 190.5 to 188 (Median/Average Values) Day Lead From Order to Commissioning
(it took only about 9 to 10 days to go from order to keel laying for this class, which is why they bend the curve)
(Fastest was built in 147 days from order to commissioning)

Type IIB: 407.5 to 476.5 (Median/Average Values) Day Lead From Order to Commissioning.
(Fastest was built in 301 days from order to commissioning)

Type IIC: 678 to 698.25 (Median/Average Values) Day Lead From Order to Commissioning.
(Fastest was built in 527 days from order to commissioning)

Type IID: 380 to 379.56 (Median/Average Values) Day Lead From Order to Commissioning.
(Fastest was built in 264 days from order to commissioning)

Type IX: 904.5 to 909.75 (Median/Average Values) Day Lead From Order to Commissioning.
(Fastest was built in 736 days from order to commissioning)

Type IXB: 875 to 845.78 (Median/Average Values) Day Lead From Order to Commissioning.
(Fastest was built in 499 days from order to commissioning)

Type IXC: 710 to 711.98 (Median/Average Values) Day Lead From Order to Commissioning.
(Fastest was built in 514 days from order to commissioning)

Type IXC/40: 772 to 777.25 (Median/Average Values) Day Lead From Order to Commissioning.
(Fastest was built in 594 days from order to commissioning)

Type IXD1: 694 Day Lead From Order to Commissioning.
(Only two built; Fastest was built in 670 days from order to commissioning)

Type IXD2: 789 to 798.5 (Median/Average Values) Day Lead From Order to Commissioning.
(Fastest was built in 627 days from order to commissioning)

Type IXD/42: 1,090 days Lead From Order to Commissioning.
(Only one built)

Type VIIA: 572.5 to 580.8 (Median/Average Values) Day Lead From Order to Commissioning.
(Fastest was built in 488 days from order to commissioning)

Type VIIB: 873 to 881.16 (Median/Average Values) Day Lead From Order to Commissioning.
(Fastest was built in 581 days from order to commissioning)

Type VIIC: 709 to 734.7 (Median/Average Values) Day Lead From Order to Commissioning.
(Fastest was built in 409 days from order to commissioning)

Type VIIC/41: 737 to 760.4 (Median/Average Values) Day Lead From Order to Commissioning.
(Fastest was built in 595 days from order to commissioning)

Type VIID Minelayer: 656.5 to 653.5 (Median/Average Values) Day Lead From Order to Commissioning.
(Fastest was built in 561 days from order to commissioning)

Type VIIF Torpedo Transport: 645.5 to 658.75 (Median/Average Values) Day Lead From Order to Commissioning.
(Fastest was built in 614 days from order to commissioning)

Type XB Mine Layer: 983.5 to 991.875 (Median/Average Values) Day Lead From Order to Commissioning.
(Fastest was built in 858 days from order to commissioning)

Type XIV Milk Cow: 597 to 594.6 (Median/Average Values) Day Lead From Order to Commissioning.
(Fastest was built in 522 days from order to commissioning)

Type XVIIA (Wa201 Walter): 595 Day Lead From Order to Commissioning.
(Only Two Built; fastest was built in 515 days from order to commissioning)

Type XVIIA (Wk202 Walter): 544 Day Lead From Order to Commissioning.
(Only Two Built; fastest was built in 464 days from order to commissioning)

Type XVIIB Walter Boat: 766 to 760.6 (Median/Average Values) Day Lead From Order to Commissioning.
(Fastest was built in 717 days from order to commissioning)

Type XXI Walter Boat: 415.5 to 408.15 (Median/Average Values) Day Lead From Order to Commissioning.
(Fastest was built in 234 days from order to commissioning)

Type XXIII Walter Boat: 239 to 248.49 (Median/Average Values) Day Lead From Order to Commissioning.
(Fastest was built in 75 days from order to commissioning)
User avatar
AlvaroSousa
Posts: 12107
Joined: Mon Jul 29, 2013 7:13 pm
Contact:

RE: Unit Production Times

Post by AlvaroSousa »

I can't do anything like that. You can change the length of build time that they come out though in the editor.
Creator Kraken Studios
- WarPlan
- WarPlan Pacific

Designer Strategic Command
- Brute Force (mod) SC2
- Assault on Communism SC2
- Assault on Democracy SC2
- Map Image Importer SC3
Post Reply

Return to “WarPlan”